Understand the system
How it works
AI load is not supplied by a contract alone: electrons require generation, wires, interconnection, protection, and hour-by-hour reliability in the same place and time.
Delivering power to the campus
Select a capability to explore its role and connections.
Selected: Generation & storage
Generation & storage
Electricity generation, storage, flexibility, and reliability resources serving new load.
Explore Generation & storage in AtlasDocumented connections
- Generation & storage → Grid interconnection
Generation and storage reach load through interconnection and transmission networks.
Relationship evidence · 5
- [1] The IEA estimates that global data-center electricity consumption rose 17 percent in 2025, with AI-focused data centers growing faster.
- [2] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [4] The NRC regulates the design, siting, construction, and operation of new commercial nuclear facilities through requirements, licensing, and oversight, with formal opportunities for public involvement.
- [5] The IEA's 2025 base case projects worldwide data-center electricity demand to more than double to about 945 TWh by 2030.
Selected documented dependencies. Arrows retain their Atlas direction; they do not represent quantities or a complete engineering process.
A large AI campus behaves like an industrial load with rapid growth, high availability expectations, and concentrated geography. Meeting it requires more than annual energy matching. Utilities and grid operators must study substations and transmission, plan resource adequacy, manage power quality, and allocate upgrade costs while generation and storage projects navigate their own queues and construction schedules.
Energy and capacity differ
Annual MWh describe energy; serving peak demand requires dependable capacity, ramping, reserves, and network deliverability. A portfolio can be energy-matched yet constrained during critical hours.
- Hourly demand and supply matter beyond annual totals
- Nameplate, accredited, and delivered capacity are different measures
Supporting evidence · 7
- [1] Data centers used about 415 TWh of electricity worldwide in 2024, around 1.5 percent of global electricity consumption.
- [2] The IEA estimates that global data-center electricity consumption rose 17 percent in 2025, with AI-focused data centers growing faster.
- [3] U.S. data centers consumed an estimated 176 TWh in 2023, equal to roughly 4.4 percent of national electricity use.
- [4] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- [5] IEA estimates that the physical generation supplying global data centers in 2024 was approximately 30 percent coal, 27 percent renewables, 26 percent gas, and 15 percent nuclear; rounding and other sources account for the remainder.
- [6] Ireland's regulator reports that data centers increased from 5 percent of national electricity demand in 2015 to 22 percent in 2024.
- [7] Ireland's regulator projects contracted data-center demand rising to 14.6 TWh in 2034, equal to 31 percent of national electricity demand under the cited outlook.
Interconnection is a queue
New generation must be studied for network impacts before connecting. Cluster studies and readiness rules aim to reduce speculative backlog, but FERC's June 2026 status statement confirms that transmission-provider compliance was still incomplete; effective law and fully implemented tariffs are separate milestones.
- Map load and generation queues together
- Expose network-upgrade cost responsibility
Supporting evidence · 4
- [1] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- [2] FERC's chair stated on June 18, 2026 that compliance with Order No. 2023 was not yet fully complete across transmission providers.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [4] At year-end 2024, about 10,300 active U.S. transmission-interconnection projects represented roughly 1,400 GW of generation and 890 GW of storage in queues covered by LBNL's dataset.
The campus meets the grid
Transmission lines feed substations, transformers step voltage down, switchgear protects circuits, and backup systems bridge interruptions. Redundancy choices affect cost, emissions, and local resilience.
- Trace voltage from grid to accelerator
- Include losses, backup tests, and failure modes
Supporting evidence · 4
- [1] NVIDIA's DGX GB200 documentation describes a rack-scale system with 72 GPUs, 36 Grace CPUs, and an approximately 120 kW power envelope, with liquid cooling alongside air-cooled components.
- [2] Open Compute Project workstreams are addressing future AI rack power envelopes from 250 kW toward 1 MW alongside liquid-cooling standards.
- [3] The NRC regulates the design, siting, construction, and operation of new commercial nuclear facilities through requirements, licensing, and oversight, with formal opportunities for public involvement.
- [4] Virginia JLARC's modeled data-center buildout scenarios place added generation- and transmission-related cost for a typical Dominion residential customer at $14 to $37 per month in real dollars by 2040.
Flexibility can become infrastructure
Workload shifting, power capping, staged energization, batteries, and geographic scheduling can reduce coincident peaks when service requirements permit. One Phoenix study measured a twenty-five-percent cluster reduction for three hours, but that bounded result is not a fleet or whole-facility guarantee. PJM's current regional rules, FERC-hosted baseline guidance, and DOE's waveform-monitoring analysis show that qualification also requires defined meter boundaries, interval data, response duration, baseline error, rebound, and telemetry matched to the event frequency.
- Record response duration, rebound, and service limits
- Verify delivered flexibility at the grid meter
Supporting evidence · 7
- [1] The IEA's 2025 base case projects worldwide data-center electricity demand to more than double to about 945 TWh by 2030.
- [2] On June 18, 2026, FERC opened targeted proceedings for six RTOs and ISOs to justify or reform large-load interconnection practices, including flexible service, cost-allocation, and co-location questions.
- [3] Lawrence Berkeley National Laboratory's demand-flexibility maturity model treats evaluation, measurement and verification plus enabling data infrastructure as distinct capabilities required for dependable flexible-load programs.
- [4] FERC-hosted measurement guidance treats demand reduction as observed load relative to an estimated counterfactual baseline, requires error to be characterized, and identifies post-event rebound as a separate measurable effect.
- [5] PJM's July 2026 operating manual requires product-specific demand-response registration, event notification, meter data, settlement, and interval-meter or approved submeter treatment within its regional market rules.
- [6] DOE reports that standard phasor-measurement filtering can miss or distort higher-frequency AI-load oscillations, while point-on-wave measurement preserves the waveform at materially higher communications and storage cost; a hybrid approach serves different monitoring bands.
- [7] A field demonstration on one 256-GPU cluster in a commercial Phoenix facility reduced cluster power by 25 percent for three hours while maintaining the study's defined quality-of-service guarantees.
Featured evidence
Evidence in context
U.S. interconnection-queue capacity at year-end 2024
LBNL compilation of proposed generation and storage capacity actively seeking transmission interconnection in U.S. queues.View chart values
| Category | Queued capacity |
|---|---|
| Generation | 1,400 GW |
| Storage | 890 GW |
Key indicators
Key measures & constraints
- 01
The IEA estimates that global data-center electricity consumption rose 17 percent in 2025, with AI-focused data centers growing faster.
- Class
- estimate
- Geography
- Global
- Period
- 2025
- Confidence
- high
- 02
LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- Class
- projection
- Geography
- United States
- Period
- 2030
- Confidence
- medium
- 03
On June 18, 2026, FERC opened targeted proceedings for six RTOs and ISOs to justify or reform large-load interconnection practices, including flexible service, cost-allocation, and co-location questions.
- Class
- fact
- Geography
- United States
- Period
- June 18, 2026 orders
- Confidence
- high
- 04
At year-end 2024, about 10,300 active U.S. transmission-interconnection projects represented roughly 1,400 GW of generation and 890 GW of storage in queues covered by LBNL's dataset.
- Class
- estimate
- Geography
- United States
- Period
- Year-end 2024
- Confidence
- high
- 05
A field demonstration on one 256-GPU cluster in a commercial Phoenix facility reduced cluster power by 25 percent for three hours while maintaining the study's defined quality-of-service guarantees.
- Class
- fact
- Geography
- Phoenix, Arizona, United States
- Period
- 2025 field demonstration lasting three hours
- Confidence
- medium
System map
Connections across the system
Explore inputs, outputs, and shared capabilities in the Atlas. Open the register for every documented relationship.
Enters this system 8
- AI workload demand→ Project capitalTrace relationship
- AI workload demand→ Generation & storageTrace relationship
Leaves this system 6
- Leading-edge fab← Project capitalTrace relationship
- Data-center campus← Grid interconnectionTrace relationship
Shared capabilities can belong to more than one System. These links carry materials, energy, information, capital, or permissions; they describe dependencies, not quantities or a complete process model.
Explore 10 capabilities and operating boundaries
All documented relationships · 23
- criticaloutput
Long-duration capital funds fab construction, tools, and ramp.
Trace relationship - criticaloutput
Substations and transmission upgrades deliver usable electrical capacity to campus.
Trace relationshipSupporting evidence · 3
- [1] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- [2] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- criticalinternal
Generation and storage reach load through interconnection and transmission networks.
Trace relationshipSupporting evidence · 5
- [1] The IEA estimates that global data-center electricity consumption rose 17 percent in 2025, with AI-focused data centers growing faster.
- [2] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [4] The NRC regulates the design, siting, construction, and operation of new commercial nuclear facilities through requirements, licensing, and oversight, with formal opportunities for public involvement.
- [5] The IEA's 2025 base case projects worldwide data-center electricity demand to more than double to about 945 TWh by 2030.
- criticaloutput
Land, water, fiscal, and construction decisions condition campus development.
Trace relationshipSupporting evidence · 4
- [1] LBNL estimated average U.S. data-center site water usage effectiveness at just over 0.36 liters per kWh through 2023.
- [2] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [4] In Pew's 2026 U.S. data-center survey, 39 percent called data centers mostly bad for the environment, 38 percent mostly bad for home energy costs, and 30 percent mostly bad for nearby quality of life.
- criticalinternal
Transmission delivers bulk power into substations and local distribution networks.
Trace relationshipSupporting evidence · 2
- [1] At year-end 2024, about 10,300 active U.S. transmission-interconnection projects represented roughly 1,400 GW of generation and 890 GW of storage in queues covered by LBNL's dataset.
- [2] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- criticaloutput
Distribution service and substations deliver usable utility capacity to the campus boundary.
Trace relationshipSupporting evidence · 2
- [1] The U.S. Department of Energy reports that distribution-transformer lead times expanded from roughly three to six months in 2019 to twelve to thirty months in 2023.
- [2] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- importantinput
Forecast demand unlocks financing and procurement commitments.
Trace relationship - importantinput
Workload forecasts become regional electricity requirements.
Trace relationshipSupporting evidence · 3
- [1] The IEA estimates that global data-center electricity consumption rose 17 percent in 2025, with AI-focused data centers growing faster.
- [2] The IEA's 2025 base case projects worldwide data-center electricity demand to more than double to about 945 TWh by 2030.
- [3] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- importantoutput
Project finance funds site, shell, utilities, and commissioning.
Trace relationship - importantinput
Participation and local evidence shape conditions, legitimacy, and oversight.
Trace relationshipSupporting evidence · 3
- [1] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- [2] In Pew's 2026 U.S. data-center survey, 39 percent called data centers mostly bad for the environment, 38 percent mostly bad for home energy costs, and 30 percent mostly bad for nearby quality of life.
- [3] In the same Pew survey, 25 percent called data centers mostly good for local jobs and 23 percent mostly good for local tax revenue.
- importantinput
Capacity reservations supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] Microsoft reported $64.551 billion of property and equipment additions in fiscal 2025, compared with $44.477 billion in fiscal 2024; its fiscal year ended June 30 and the measure is not AI-only.
- [2] Amazon reported $128.3 billion of cash capital expenditure in 2025, primarily for technology infrastructure—mostly supporting AWS growth—and fulfillment capacity; the amount is not data-center-only or AI-only.
- importantinput
Project finance & risk supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- importantinternal
Transmission supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] At year-end 2024, about 10,300 active U.S. transmission-interconnection projects represented roughly 1,400 GW of generation and 890 GW of storage in queues covered by LBNL's dataset.
- [2] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- importantinternal
Distribution & substations supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] The U.S. Department of Energy reports that distribution-transformer lead times expanded from roughly three to six months in 2019 to twelve to thirty months in 2023.
- [2] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- importantinternal
Generation portfolio supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] IEA estimates that the physical generation supplying global data centers in 2024 was approximately 30 percent coal, 27 percent renewables, 26 percent gas, and 15 percent nuclear; rounding and other sources account for the remainder.
- [2] The IEA's 2025 base case projects worldwide data-center electricity demand to more than double to about 945 TWh by 2030.
- importantinternal
Grid-scale storage supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] At year-end 2024, about 10,300 active U.S. transmission-interconnection projects represented roughly 1,400 GW of generation and 890 GW of storage in queues covered by LBNL's dataset.
- [2] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- importantinternal
Tariffs, PPAs & cost allocation supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] On June 18, 2026, FERC opened targeted proceedings for six RTOs and ISOs to justify or reform large-load interconnection practices, including flexible service, cost-allocation, and co-location questions.
- [2] Virginia JLARC's modeled data-center buildout scenarios place added generation- and transmission-related cost for a typical Dominion residential customer at $14 to $37 per month in real dollars by 2040.
- importantinternal
Flexibility, telemetry & M&V supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 3
- [1] Lawrence Berkeley National Laboratory's demand-flexibility maturity model treats evaluation, measurement and verification plus enabling data infrastructure as distinct capabilities required for dependable flexible-load programs.
- [2] FERC-hosted measurement guidance treats demand reduction as observed load relative to an estimated counterfactual baseline, requires error to be characterized, and identifies post-event rebound as a separate measurable effect.
- [3] PJM's July 2026 operating manual requires product-specific demand-response registration, event notification, meter data, settlement, and interval-meter or approved submeter treatment within its regional market rules.
- importantinput
Environmental permitting supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 3
- [1] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [2] A July 2025 U.S. executive order directs agencies to review categorical exclusions, use FAST-41 processes where eligible, support brownfield guidance, and examine federal sites for data-center infrastructure; those mechanisms do not themselves constitute project approval.
- [3] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- importantinput
Grid regulation supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 3
- [1] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- [2] On June 18, 2026, FERC opened targeted proceedings for six RTOs and ISOs to justify or reform large-load interconnection practices, including flexible service, cost-allocation, and co-location questions.
- [3] FERC's chair stated on June 18, 2026 that compliance with Order No. 2023 was not yet fully complete across transmission providers.
- importantinput
Benefit agreements & commitments supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] St. Louis's April 2026 conditional approval for the Armory data-center project included closed-loop and air-cooled water design, noise and generator limits, PUE thresholds, annual heat-rejection and reuse reporting, certified e-waste handling, decommissioning, escalating 20-year job minimums, and financial or occupancy remedies for specified shortfalls.
- [2] Virginia JLARC found that most data centers used no more water than an average large office building, while a few used substantially more, and recommended explicit local authority to require water-use estimates before development approval.
- importantinternal
Verified workload response can modify the timing and operating profile of grid demand.
Trace relationshipSupporting evidence · 2
- [1] Lawrence Berkeley National Laboratory's demand-flexibility maturity model treats evaluation, measurement and verification plus enabling data infrastructure as distinct capabilities required for dependable flexible-load programs.
- [2] A field demonstration on one 256-GPU cluster in a commercial Phoenix facility reduced cluster power by 25 percent for three hours while maintaining the study's defined quality-of-service guarantees.
- importantoutput
Tariff and cost-allocation choices determine how infrastructure costs reach other customers.
Trace relationshipSupporting evidence · 2
- [1] On June 18, 2026, FERC opened targeted proceedings for six RTOs and ISOs to justify or reform large-load interconnection practices, including flexible service, cost-allocation, and co-location questions.
- [2] Virginia JLARC's modeled data-center buildout scenarios place added generation- and transmission-related cost for a typical Dominion residential customer at $14 to $37 per month in real dollars by 2040.
Named companies + institutions
Organizations & their roles
- principal · public company
Alphabet
Alphabet Inc.Technology holding company whose Google businesses procure and operate global AI compute and cloud infrastructure.
Roles, locations & evidence
- Role
- financier
- Products / service
- Technical infrastructure capital investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Alphabet's filing-backed operating portfolio includes technical infrastructure capital investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
- principal · public company
Amazon / AWS
Amazon.com, Inc.Commerce and cloud company whose AWS segment is a major buyer and operator of AI compute, network, and data-center capacity.
Roles, locations & evidence
- Role
- financier
- Products / service
- AWS infrastructure capital investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Amazon / AWS's filing-backed operating portfolio includes aws infrastructure capital investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
- principal · public company
Meta
Meta Platforms, Inc.Digital-platform company that designs, procures, and operates large AI training and inference infrastructure.
Roles, locations & evidence
- Role
- financier
- Products / service
- AI infrastructure capital investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Meta's filing-backed operating portfolio includes ai infrastructure capital investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
- principal · public company
Microsoft
Microsoft CorporationGlobal cloud and software company that procures, finances, and operates large-scale AI infrastructure.
Roles, locations & evidence
- Role
- financier
- Products / service
- Data-center and compute infrastructure investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Microsoft's filing-backed operating portfolio includes data-center and compute infrastructure investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
All other organizations · 8
- principal · nonprofit
PJM Interconnection
PJM Interconnection, L.L.C.Regional transmission organization coordinating wholesale power markets and grid operations across a multi-state U.S. footprint.
Roles, locations & evidence
- Role
- operator
- Products / service
- regional grid and demand-response market operations
- Documented activity
- PJM Interconnection
- Headquarters
- United States
Why this organization belongs in the System- Grid interconnection
Primary-source evidence connects this institution to regional grid and demand-response market operations in the specified Atlas capability.
- principal · regulator
U.S. NRC
United States Nuclear Regulatory CommissionIndependent U.S. regulator responsible for licensing and oversight of civilian nuclear reactors.
Roles, locations & evidence
- Role
- regulator
- Products / service
- new nuclear reactor licensing
- Documented activity
- United States
- Headquarters
- United States
Why this organization belongs in the System- Generation portfolio
Primary-source evidence connects this institution to new nuclear reactor licensing in the specified Atlas capability.
- material · public company
Constellation Energy
Constellation Energy CorporationCompetitive electricity producer and supplier with a large nuclear fleet and commercial energy-services business.
Roles, locations & evidence
- Role
- offtaker · supplier · operator
- Products / service
- Long-term energy supply agreements · Wholesale and retail electricity supply · Nuclear and other electric generation
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Tariffs, PPAs & cost allocation
Constellation Energy's filing-backed operating portfolio includes long-term energy supply agreements; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Generation & storage
Constellation Energy's filing-backed operating portfolio includes wholesale and retail electricity supply; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Generation portfolio
Constellation Energy's filing-backed operating portfolio includes nuclear and other electric generation; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- material · government
DOE Office of Electricity
United States Department of Energy Office of ElectricityU.S. government office supporting electric-grid reliability, resilience, monitoring, and supply-chain analysis.
Roles, locations & evidence
- Role
- standards setter
- Products / service
- large-load oscillation monitoring guidance
- Documented activity
- United States
- Headquarters
- United States
Why this organization belongs in the System- Flexibility, telemetry & M&V
Primary-source evidence connects this institution to large-load oscillation monitoring guidance in the specified Atlas capability.
- material · research institution
Lawrence Berkeley National Laboratory
U.S. national laboratory researching data-center energy use, demand flexibility, and electricity systems.
Roles, locations & evidence
- Role
- standards setter
- Products / service
- demand-flexibility measurement framework · data-center electricity-use research
- Documented activity
- United States
- Headquarters
- United States
Why this organization belongs in the System- Flexibility, telemetry & M&V
Primary-source evidence connects this institution to demand-flexibility measurement framework in the specified Atlas capability.
- Generation & storage
Primary-source evidence connects this institution to data-center electricity-use research in the specified Atlas capability.
- material · public company
NextEra Energy
NextEra Energy, Inc.Energy company spanning regulated utility operations and competitive generation, storage, and energy infrastructure.
Roles, locations & evidence
- Role
- offtaker · operator
- Products / service
- Power purchase agreements and utility service · Renewable, gas, and nuclear generation · Utility-scale battery storage
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Tariffs, PPAs & cost allocation
NextEra Energy's filing-backed operating portfolio includes power purchase agreements and utility service; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Generation portfolio
NextEra Energy's filing-backed operating portfolio includes renewable, gas, and nuclear generation; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Grid-scale storage
NextEra Energy's filing-backed operating portfolio includes utility-scale battery storage; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- representative · public company
Dominion Energy
Dominion Energy, Inc.Regulated energy company serving electricity demand in Virginia and other U.S. jurisdictions with major data-center load.
Roles, locations & evidence
- Role
- operator · supplier
- Products / service
- Regulated electric distribution · Electric generation and utility service · Regulated tariffs and large-load service
- Documented activity
- Virginia · PJM Interconnection
- Headquarters
- Virginia
Why this organization belongs in the System- Distribution & substations
Dominion Energy's filing-backed operating portfolio includes regulated electric distribution; the listed places are explicit role geographies, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Generation & storage
Dominion Energy's filing-backed operating portfolio includes electric generation and utility service; the listed places are explicit role geographies, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Tariffs, PPAs & cost allocation
Dominion Energy's filing-backed operating portfolio includes regulated tariffs and large-load service; the listed places are explicit role geographies, and headquarters is not used as a proxy. Representative status does not imply market rank.
- representative · public company
Duke Energy
Duke Energy CorporationRegulated U.S. electric and gas utility serving large regional loads through generation, transmission, and distribution assets.
Roles, locations & evidence
- Role
- operator
- Products / service
- Electric distribution and substations · Regulated electric generation · Regulated utility tariffs
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Distribution & substations
Duke Energy's filing-backed operating portfolio includes electric distribution and substations; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Generation portfolio
Duke Energy's filing-backed operating portfolio includes regulated electric generation; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Tariffs, PPAs & cost allocation
Duke Energy's filing-backed operating portfolio includes regulated utility tariffs; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
Affected policies
Relevant policies
Legal status is separated from policy objective. Every record keeps its jurisdiction, mechanism, affected nodes, and verification date.
- effective
U.S. CHIPS and Science Act incentives
Expand domestic semiconductor manufacturing, research, workforce, and supply-chain resilience.
Mechanism, scope & sources
Manufacturing grants, loans and guarantees, research programs, and an investment tax credit with program conditions; current project records distinguish proposed and final awards, with disbursement tied to milestones.
United StatesOpen full policy record - effective
European Chips Act
Strengthen European semiconductor capacity, research leadership, monitoring, and crisis response.
Mechanism, scope & sources
Coordinates the Chips for Europe initiative, first-of-a-kind facility support, supply monitoring, and crisis tools; the Commission's Chips Act 2.0 work remains a proposal rather than replacement law.
European UnionOpen full policy record - effective
FERC Order No. 2023 generator interconnection reform
Reduce interconnection backlog and improve the speed and certainty of connecting new generation.
Mechanism, scope & sources
Requires cluster studies, readiness deposits, withdrawal penalties, transmission-provider delay penalties, and affected-system reforms through transmission-provider tariff compliance that remained incomplete in June 2026.
United States interstate transmissionOpen full policy record
Read this System in the field guide
Continue in the Volumes
Start with three selected readings, or explore the complete reading list.
Continue the Plant → Power → Atlas journey
Read the power train in Plant Explore grid interconnection in the AtlasComplete reading list
Plant
3 spreadsPermission
1 spreadsEvidence & review
currentEvidence health46 active claims · next review Oct 13, 2026+
- Active claims
- 46
- Sources
- 47
- High volatility
- 17
- Next review
- Oct 13, 2026
- Due soon
- 0
- Overdue
- 0
- Superseded
- 0