Understand the system
How it works
A data center is a site-specific industrial system whose usable compute is bounded by construction sequencing, utility delivery, and safe removal of heat.
The campus and its cooling dependencies
Select a capability to explore its role and connections.
Selected: Water system
Water system
Site water supply, treatment, cooling use, discharge, reuse, and seasonal constraints.
Explore Water system in AtlasDocumented connections
- Water system → Liquid cooling
Water availability and cooling architecture shape heat-rejection options.
Selected documented dependencies. Arrows retain their Atlas direction; they do not represent quantities or a complete engineering process.
The data-center campus is where global supply chains meet local geology, weather, roads, water systems, fiber routes, power networks, labor markets, and permitting. Developers must sequence grading, shells, substations, generators, cooling plants, white space, racks, and commissioning around long-lead equipment. Higher rack density moves cooling from room-scale airflow toward direct liquid loops and changes every interface from the chip to the heat sink.
Site selection is systems engineering
Power, fiber, hazard exposure, land, water, workforce, tax, permitting, and community context interact. A cheap parcel can be expensive once delivery risks are priced. Federal review mechanisms such as FAST-41 may coordinate eligible projects, but a directive or portfolio listing is not a permit and does not remove site-specific standards.
- Constraints and externalities belong in one site decision
- Enabling infrastructure has an identifiable cost bearer
Supporting evidence · 5
- [1] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- [2] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [4] A July 2025 U.S. executive order directs agencies to review categorical exclusions, use FAST-41 processes where eligible, support brownfield guidance, and examine federal sites for data-center infrastructure; those mechanisms do not themselves constitute project approval.
- [5] In Pew's 2026 U.S. data-center survey, 39 percent called data centers mostly bad for the environment, 38 percent mostly bad for home energy costs, and 30 percent mostly bad for nearby quality of life.
Construction follows the critical path
Substations, switchgear, transformers, generators, chillers, coolant distribution, controls, and racks have different lead times. Phased delivery can unlock capacity while later blocks continue.
- Schedule gates follow the longest-lead equipment
- Building completion is not commissioned capacity
Supporting evidence · 5
- [1] Intel characterizes a modern fab as an investment of roughly 10 billion dollars that can take three to five years to build.
- [2] Global investment in data centers reached roughly half a trillion U.S. dollars in 2024, nearly double the 2022 level.
- [3] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- [4] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [5] OpenAI and developer Crusoe describe the Stargate campus in Abilene, Texas as operating: Crusoe reported the first phase live and its first two buildings energized by September 2025, while OpenAI stated in April 2026 that the site operates on Oracle Cloud Infrastructure with NVIDIA GB200 systems.
Cooling is a chain
Heat moves from silicon through package interfaces, cold plates or air, coolant loops, facility water, and finally the atmosphere. The weakest interface limits safe rack power.
- Trace heat from junction to ambient air
- Compare air, direct-liquid, and hybrid boundaries
Supporting evidence · 2
- [1] NVIDIA's DGX GB200 documentation describes a rack-scale system with 72 GPUs, 36 Grace CPUs, and an approximately 120 kW power envelope, with liquid cooling alongside air-cooled components.
- [2] Open Compute Project workstreams are addressing future AI rack power envelopes from 250 kW toward 1 MW alongside liquid-cooling standards.
Water metrics need boundaries
Site WUE varies by cooling architecture, climate, utilization, water source, and season; electricity generation can add off-site water effects. Prince William County's records make the scale problem concrete: 25 operating buildings averaged about 18,000 gallons per building-day, reached about 88,000 gallons on a maximum day, and represented different shares of average-day and maximum-day system demand. A single annual ratio cannot describe that local peak or allocation boundary.
- Label site and source water separately
- Report seasonal withdrawals and consumption
Supporting evidence · 3
- [1] LBNL estimated average U.S. data-center site water usage effectiveness at just over 0.36 liters per kWh through 2023.
- [2] U.S. data centers consumed an estimated 176 TWh in 2023, equal to roughly 4.4 percent of national electricity use.
- [3] Prince William County reported that Service Authority records for 25 operating data-center buildings showed about 18,000 gallons per building on an average day and about 88,000 gallons on a maximum day; together, the buildings represented about 1.5 percent of system average-day demand and 3.9 percent of maximum-day demand.
Featured evidence
Evidence in context
Modeled U.S. data-center average PUE
LBNL modeled stock-average PUE for 2014 and 2023, followed by a projected 2028 range under lower- and higher-efficiency cases.View chart values
| Category | Average PUE |
|---|---|
| 2014 modeled | 1.6 PUE ratio |
| 2023 modeled | 1.4 PUE ratio |
| 2028 projected low | 1.15 PUE ratio |
| 2028 projected high | 1.35 PUE ratio |
Key indicators
Key measures & constraints
- 01
LBNL estimated average U.S. data-center site water usage effectiveness at just over 0.36 liters per kWh through 2023.
- Class
- estimate
- Geography
- United States
- Period
- through 2023
- Confidence
- medium
- 02
LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- Class
- projection
- Geography
- United States
- Period
- 2030
- Confidence
- medium
- 03
EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- Class
- stakeholder position
- Geography
- United States
- Period
- January 2026 guidance
- Confidence
- high
- 04
Open Compute Project workstreams are addressing future AI rack power envelopes from 250 kW toward 1 MW alongside liquid-cooling standards.
- Class
- projection
- Geography
- Global
- Period
- 2025 roadmap
- Confidence
- medium
- 05
LBNL's modeled annual-average U.S. data-center PUE declined from 1.6 in 2014 to 1.4 in 2023.
- Class
- estimate
- Geography
- United States
- Period
- 2014 to 2023
- Confidence
- high
System map
Connections across the system
Explore inputs, outputs, and shared capabilities in the Atlas. Open the register for every documented relationship.
Enters this system 12
- Grid interconnection→ Data-center campusTrace relationship
- Distribution & substations→ Data-center campusTrace relationship
Leaves this system 3
- Leading-edge fab← Project capitalTrace relationship
- AI rack system← Liquid coolingTrace relationship
Shared capabilities can belong to more than one System. These links carry materials, energy, information, capital, or permissions; they describe dependencies, not quantities or a complete process model.
Explore 11 capabilities and operating boundaries
All documented relationships · 25
- criticaloutput
Long-duration capital funds fab construction, tools, and ramp.
Trace relationship - criticalinput
Substations and transmission upgrades deliver usable electrical capacity to campus.
Trace relationshipSupporting evidence · 3
- [1] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- [2] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- criticalinternal
Land, water, fiscal, and construction decisions condition campus development.
Trace relationshipSupporting evidence · 4
- [1] LBNL estimated average U.S. data-center site water usage effectiveness at just over 0.36 liters per kWh through 2023.
- [2] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- [3] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [4] In Pew's 2026 U.S. data-center survey, 39 percent called data centers mostly bad for the environment, 38 percent mostly bad for home energy costs, and 30 percent mostly bad for nearby quality of life.
- criticalinternal
Transformers and switchgear convert utility service into protected campus distribution.
Trace relationshipSupporting evidence · 2
- [1] The U.S. Department of Energy reports that distribution-transformer lead times expanded from roughly three to six months in 2019 to twelve to thirty months in 2023.
- [2] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- criticalinput
Distribution service and substations deliver usable utility capacity to the campus boundary.
Trace relationshipSupporting evidence · 2
- [1] The U.S. Department of Energy reports that distribution-transformer lead times expanded from roughly three to six months in 2019 to twelve to thirty months in 2023.
- [2] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- importantinput
Forecast demand unlocks financing and procurement commitments.
Trace relationship - importantinternal
Project finance funds site, shell, utilities, and commissioning.
Trace relationship - importantinput
Rack power, mass, cooling, and service envelopes constrain facility design.
Trace relationshipSupporting evidence · 2
- [1] NVIDIA's DGX GB200 documentation describes a rack-scale system with 72 GPUs, 36 Grace CPUs, and an approximately 120 kW power envelope, with liquid cooling alongside air-cooled components.
- [2] Open Compute Project workstreams are addressing future AI rack power envelopes from 250 kW toward 1 MW alongside liquid-cooling standards.
- importantoutput
Liquid loops capture and transport heat from high-density rack components.
Trace relationshipSupporting evidence · 2
- [1] NVIDIA's DGX GB200 documentation describes a rack-scale system with 72 GPUs, 36 Grace CPUs, and an approximately 120 kW power envelope, with liquid cooling alongside air-cooled components.
- [2] Open Compute Project workstreams are addressing future AI rack power envelopes from 250 kW toward 1 MW alongside liquid-cooling standards.
- importantinternal
Water availability and cooling architecture shape heat-rejection options.
Trace relationship - importantinput
Participation and local evidence shape conditions, legitimacy, and oversight.
Trace relationshipSupporting evidence · 3
- [1] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- [2] In Pew's 2026 U.S. data-center survey, 39 percent called data centers mostly bad for the environment, 38 percent mostly bad for home energy costs, and 30 percent mostly bad for nearby quality of life.
- [3] In the same Pew survey, 25 percent called data centers mostly good for local jobs and 23 percent mostly good for local tax revenue.
- importantoutput
Specialized engineering and technician capability enables ramp and operations.
Trace relationshipSupporting evidence · 2
- importantinternal
Skilled trades, commissioning, controls, and operations turn assets into capacity.
Trace relationship - importantinput
Capacity reservations supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] Microsoft reported $64.551 billion of property and equipment additions in fiscal 2025, compared with $44.477 billion in fiscal 2024; its fiscal year ended June 30 and the measure is not AI-only.
- [2] Amazon reported $128.3 billion of cash capital expenditure in 2025, primarily for technology infrastructure—mostly supporting AWS growth—and fulfillment capacity; the amount is not data-center-only or AI-only.
- importantinput
Project finance & risk supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- importantinternal
Land & site permitting supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [2] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- importantinternal
EPC & construction supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] Global investment in data centers reached roughly half a trillion U.S. dollars in 2024, nearly double the 2022 level.
- [2] St. Louis's April 2026 conditional approval for the Armory data-center project included closed-loop and air-cooled water design, noise and generator limits, PUE thresholds, annual heat-rejection and reuse reporting, certified e-waste handling, decommissioning, escalating 20-year job minimums, and financial or occupancy remedies for specified shortfalls.
- importantinternal
Transformers & switchgear supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] The U.S. Department of Energy reports that distribution-transformer lead times expanded from roughly three to six months in 2019 to twelve to thirty months in 2023.
- [2] NVIDIA's DGX GB200 documentation describes a rack-scale system with 72 GPUs, 36 Grace CPUs, and an approximately 120 kW power envelope, with liquid cooling alongside air-cooled components.
- importantinternal
UPS, batteries & backup supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] LBNL's 2025 Update places U.S. data-center electricity use at 649 TWh in its 2030 Reference Case, with compounded-uncertainty bounds of 521 to 843 TWh, or 9.5 to 15.3 percent of U.S. electricity use.
- [2] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- importantinternal
Heat rejection supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 3
- [1] LBNL's modeled annual-average U.S. data-center PUE declined from 1.6 in 2014 to 1.4 in 2023.
- [2] LBNL scenarios place annual-average U.S. data-center PUE between 1.15 and 1.35 in 2028.
- [3] LBNL estimated average U.S. data-center site water usage effectiveness at just over 0.36 liters per kWh through 2023.
- importantinput
Environmental permitting supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 3
- [1] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- [2] A July 2025 U.S. executive order directs agencies to review categorical exclusions, use FAST-41 processes where eligible, support brownfield guidance, and examine federal sites for data-center infrastructure; those mechanisms do not themselves constitute project approval.
- [3] EPA's January 2026 redevelopment guidance says candidate data-center sites must fit site conditions, reach power and fiber, comply with applicable regulation and cleanup controls, and incorporate planning and community input.
- importantinput
Grid regulation supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 3
- [1] FERC Order No. 2023 requires cluster studies, greater project-readiness requirements, and transmission-provider delay penalties for generator interconnection.
- [2] On June 18, 2026, FERC opened targeted proceedings for six RTOs and ISOs to justify or reform large-load interconnection practices, including flexible service, cost-allocation, and co-location questions.
- [3] FERC's chair stated on June 18, 2026 that compliance with Order No. 2023 was not yet fully complete across transmission providers.
- importantinput
Benefit agreements & commitments supplies a distinct operating capability within its broader Atlas system.
Trace relationshipSupporting evidence · 2
- [1] St. Louis's April 2026 conditional approval for the Armory data-center project included closed-loop and air-cooled water design, noise and generator limits, PUE thresholds, annual heat-rejection and reuse reporting, certified e-waste handling, decommissioning, escalating 20-year job minimums, and financial or occupancy remedies for specified shortfalls.
- [2] Virginia JLARC found that most data centers used no more water than an average large office building, while a few used substantially more, and recommended explicit local authority to require water-use estimates before development approval.
- importantinput
Financing terms depend on land control, permits, utility milestones, and construction risk.
Trace relationshipSupporting evidence · 2
- [1] Global investment in data centers reached roughly half a trillion U.S. dollars in 2024, nearly double the 2022 level.
- [2] CRS finds that individual data centers typically fall under state and local siting, while the federal permitting nexus varies by project; FERC, NRC, the Army Corps, and delegated air and water programs may apply depending on configuration and location.
- importantinput
Enforceable commitments can become conditions of site approval and continuing operation.
Trace relationshipSupporting evidence · 2
- [1] St. Louis's April 2026 conditional approval for the Armory data-center project included closed-loop and air-cooled water design, noise and generator limits, PUE thresholds, annual heat-rejection and reuse reporting, certified e-waste handling, decommissioning, escalating 20-year job minimums, and financial or occupancy remedies for specified shortfalls.
- [2] Virginia JLARC found that most data centers used no more water than an average large office building, while a few used substantially more, and recommended explicit local authority to require water-use estimates before development approval.
Named companies + institutions
Organizations & their roles
- principal · public company
Alphabet
Alphabet Inc.Technology holding company whose Google businesses procure and operate global AI compute and cloud infrastructure.
Roles, locations & evidence
- Role
- financier
- Products / service
- Technical infrastructure capital investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Alphabet's filing-backed operating portfolio includes technical infrastructure capital investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
- principal · public company
Amazon / AWS
Amazon.com, Inc.Commerce and cloud company whose AWS segment is a major buyer and operator of AI compute, network, and data-center capacity.
Roles, locations & evidence
- Role
- financier
- Products / service
- AWS infrastructure capital investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Amazon / AWS's filing-backed operating portfolio includes aws infrastructure capital investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
- principal · public company
Meta
Meta Platforms, Inc.Digital-platform company that designs, procures, and operates large AI training and inference infrastructure.
Roles, locations & evidence
- Role
- financier
- Products / service
- AI infrastructure capital investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Meta's filing-backed operating portfolio includes ai infrastructure capital investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
- principal · public company
Microsoft
Microsoft CorporationGlobal cloud and software company that procures, finances, and operates large-scale AI infrastructure.
Roles, locations & evidence
- Role
- financier
- Products / service
- Data-center and compute infrastructure investment
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Project capital
Microsoft's filing-backed operating portfolio includes data-center and compute infrastructure investment, and the attached quantitative operating or investment measure supports principal status at this Atlas boundary; no subregional operating place is asserted.
All other organizations · 9
- material · public company
Carrier
Carrier Global CorporationClimate and energy-solutions company supplying cooling, controls, and service systems used in buildings and data centers.
Roles, locations & evidence
- Role
- supplier
- Products / service
- Facility cooling and controls · Chillers and heat-rejection systems
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Liquid cooling
Carrier's filing-backed operating portfolio includes facility cooling and controls; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Heat rejection
Carrier's filing-backed operating portfolio includes chillers and heat-rejection systems; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- material · government
DOE Office of Electricity
United States Department of Energy Office of ElectricityU.S. government office supporting electric-grid reliability, resilience, monitoring, and supply-chain analysis.
Roles, locations & evidence
- Role
- standards setter
- Products / service
- distribution-transformer supply-chain analysis
- Documented activity
- United States
- Headquarters
- United States
Why this organization belongs in the System- Transformers & switchgear
Primary-source evidence connects this institution to distribution-transformer supply-chain analysis in the specified Atlas capability.
- material · public company
Johnson Controls
Johnson Controls International plcBuilding-systems company supplying chillers, controls, fire, security, and facility-management technologies.
Roles, locations & evidence
- Role
- supplier
- Products / service
- Building controls and commissioning services · Chillers and thermal-management systems
- Documented activity
- World
- Headquarters
- Ireland
Why this organization belongs in the System- EPC & construction
Johnson Controls's filing-backed operating portfolio includes building controls and commissioning services; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- Heat rejection
Johnson Controls's filing-backed operating portfolio includes chillers and thermal-management systems; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- material · public company
Supermicro
Super Micro Computer, Inc.Server and systems manufacturer supplying modular, rack-scale, and liquid-cooled AI infrastructure.
Roles, locations & evidence
- Role
- supplier
- Products / service
- Direct-liquid-cooled server systems
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Liquid cooling
Supermicro's filing-backed operating portfolio includes direct-liquid-cooled server systems; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- representative · private company
Crusoe
Crusoe Energy Systems LLCData-center developer and operator associated with the Abilene AI infrastructure campus.
Roles, locations & evidence
- Role
- operator
- Products / service
- Abilene data-center development and operation
- Documented activity
- United States · Texas · Abilene
- Headquarters
- United States
Why this organization belongs in the System- Data-center campus
Primary-source evidence connects this institution to abilene data-center development and operation in the specified Atlas capability. Principal status is withheld because this edition does not close a concentration, capacity, shipment, revenue, or installed-base measure for the role.
- representative · public company
Digital Realty
Digital Realty Trust, Inc.Data-center real-estate company developing and operating colocation and hyperscale facilities across global markets.
Roles, locations & evidence
- Role
- operator
- Products / service
- Colocation and hyperscale data centers
- Documented activity
- World · United States · Europe · Asia
- Headquarters
- United States
Why this organization belongs in the System- Data-center campus
Digital Realty's filing-backed operating portfolio includes colocation and hyperscale data centers; the listed places are explicit role geographies, and headquarters is not used as a proxy. Representative status does not imply market rank.
- representative · public company
Eaton
Eaton Corporation plcPower-management company supplying electrical distribution, switchgear, UPS, and power-quality systems.
Roles, locations & evidence
- Role
- manufacturer · supplier
- Products / service
- Switchgear and electrical distribution equipment · UPS and power-quality systems
- Documented activity
- World
- Headquarters
- Ireland
Why this organization belongs in the System- Transformers & switchgear
Eaton's filing-backed operating portfolio includes switchgear and electrical distribution equipment; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- UPS, batteries & backup
Eaton's filing-backed operating portfolio includes ups and power-quality systems; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- representative · public company
Equinix
Equinix, Inc.Digital-infrastructure company operating carrier-neutral data centers and interconnection services across global markets.
Roles, locations & evidence
- Role
- operator
- Products / service
- Colocation data centers
- Documented activity
- World · United States · Europe · Asia
- Headquarters
- United States
Why this organization belongs in the System- Data-center campus
Equinix's filing-backed operating portfolio includes colocation data centers; the listed places are explicit role geographies, and headquarters is not used as a proxy. Representative status does not imply market rank.
- representative · public company
Vertiv
Vertiv Holdings CoCritical-digital-infrastructure company supplying power, thermal management, and service systems for data centers.
Roles, locations & evidence
- Role
- supplier
- Products / service
- Liquid and air thermal-management systems · UPS and critical-power systems
- Documented activity
- World
- Headquarters
- United States
Why this organization belongs in the System- Liquid cooling
Vertiv's filing-backed operating portfolio includes liquid and air thermal-management systems; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
- UPS, batteries & backup
Vertiv's filing-backed operating portfolio includes ups and critical-power systems; no subregional operating place is asserted, and headquarters is not used as a proxy. Representative status does not imply market rank.
Affected policies
Relevant policies
Legal status is separated from policy objective. Every record keeps its jurisdiction, mechanism, affected nodes, and verification date.
- effective
U.S. CHIPS and Science Act incentives
Expand domestic semiconductor manufacturing, research, workforce, and supply-chain resilience.
Mechanism, scope & sources
Manufacturing grants, loans and guarantees, research programs, and an investment tax credit with program conditions; current project records distinguish proposed and final awards, with disbursement tied to milestones.
United StatesOpen full policy record - effective
European Chips Act
Strengthen European semiconductor capacity, research leadership, monitoring, and crisis response.
Mechanism, scope & sources
Coordinates the Chips for Europe initiative, first-of-a-kind facility support, supply monitoring, and crisis tools; the Commission's Chips Act 2.0 work remains a proposal rather than replacement law.
European UnionOpen full policy record
Read this System in the field guide
Continue in the Volumes
Start with three selected readings, or explore the complete reading list.
Complete reading list
Plant
12 spreads- VI · 01Site as systemOpen spread
- VI · 02Land and hazardsOpen spread
- VI · 03Reach the siteOpen spread
- VI · 04Permission to break groundOpen spread
- VI · 05Critical pathOpen spread
- VI · 06The data hallOpen spread
- VI · 07Prove the plantOpen spread
- VI · 08Heat pathOpen spread
- VI · 09Air and liquidOpen spread
- VI · 10Coolant distributionOpen spread
- VI · 11Heat rejection and waterOpen spread
- VI · 12Operate the compactOpen spread
Evidence & review
currentEvidence health42 active claims · next review Oct 13, 2026+
- Active claims
- 42
- Sources
- 49
- High volatility
- 12
- Next review
- Oct 13, 2026
- Due soon
- 0
- Overdue
- 0
- Superseded
- 0